Article info · Provisional reception

Provisional reception minutes: a completed example commented point by point

photo auteur
By Edouard Hennin, Provisional reception expert
Published on 27 May 2026 Updated on 27 May 2026 7 min read

1. The context of the example minutes

These minutes are drawn from a real (anonymised) reception of a 175 m² turnkey house in Nivelles. Reception conducted with our vastgoedexpert. 23 numbered reservations, including 3 major (roof watertightness, ventilation, earthing) and 20 minor (finishes, paint, joints).

Lifting deadline: 60 days for major reservations, 90 days for minor ones.

2. Structure of the commented minutes

The header lists the parties (buyer, contractor, expert), the contract reference, the date and the location. The description of the property follows (address, floor area, attached plan).

Then comes the table of reservations: number, room, precise location, nature of the defect, reference photo, expected lifting method, deadline. This tabular structure makes follow-up and room-by-room lifting easier.

3. The major reservations in detail

R-01 (roof watertightness): « infiltration observed at the chimney junction - bedroom 1 - 30 × 20 cm halo marks on the ceiling. Waterproofing repair + plaster/paint repair after drying. Deadline 60 d. »

R-02 (ventilation): « WC vent flow rate = 8 m³/h measured (standard NBN D 50-001 = 25 m³/h). Extractor adjustment and duct check. Deadline 30 d. »

This precision is what distinguishes enforceable minutes from a fragile document. Our reception support guarantees this level of rigour.

Questions about the example minutes

Can I copy these minutes directly?
It is a teaching template. You must adapt it to your property and defects. Our Breyne Law service provides personalised minutes.
Why anonymise?
Confidentiality of the parties (GDPR). The technical elements remain faithful to the reality of the case file.