Blog · Practical · 14 May 2026

New-build water and electricity connection: who does what

Across 612 receptions, I still see two owners out of ten arrive at commissioning without a final meter.

Freshly fitted Ores meter · Liège · April 2026 · photo Edouard Hennin
Edouard Hennin
Provisional reception expert
3 min read
Sauver Partager

Recurring question in pre-reception in my practice: “who calls Ores? who calls SWDE?”. The answer depends on the contract type — turnkey or architect-with-separate-contractors — but the trap is always the same: people wait too long. Across 612 provisional receptions supported between 2021 and 2026, I still see two owners out of ten arrive at commissioning without a final meter, which prolongs the move-in by several weeks and sometimes triggers temporary occupation charges. Here is the real responsibility split, and the calendar to follow.

Turnkey: the contractor leads, you validate

In 80% of turnkey contracts I review, the builder handles the request for temporary site connection (water and electricity), then the conversion to a final meter near the end of closed shell. Check the exact clause in the quote: some contracts bill the final connection as an extra, up to €1,800 for electricity alone and €1,200 for the SWDE connection.

Items most often billed separately:

  • Final electric connection beyond 20 metres from the street
  • Gas meter (often optional depending on the chosen heating mode)
  • Rainwater tank connected to the indoor network
  • Telecom conduit beyond the standard linear length

Read your special specifications item by item before signing: that is where the €3,000 to €5,000 surcharges hide that no one mentions in the sales office.

Architect + separate contractors: it’s you

If you manage the site with an architect but without a general builder, you open the files with Ores (or Resa depending on the municipality), SWDE and Fluvius gas if applicable. Count 8 to 12 weeks for a final electric connection after complete file submission — so to anticipate from the slab pour, not at finishing time.

The realistic calendar to hold:

  1. File Ores request: as soon as closed shell is done (waterproofing in place)
  2. SWDE request: in parallel, about 4-6 weeks lead time
  3. Fluvius gas request: 6-8 weeks, to anticipate if condensing boiler
  4. RGIE and CERGA inspection: just before the provisional reception
  5. Final commissioning: after signed reception minutes

I have seen sites in Mons and Tournai take 4 months of delay simply because the Ores request was filed 8 weeks too late. The indirect cost (extended rent, mortgage interest running on empty) was around €4,800.

At reception, demand the proofs

In the provisional reception minutes, systematically request the following four documents, ideally as signed originals:

  • Final electric meter index with dated photo
  • RGIE/AREI certificate signed by an approved body
  • CERGA gas compliance certificate (if gas boiler)
  • SWDE connection certificate or invoice of the first index

Without these four documents, commissioning is not enforceable, and you risk an interruption of supply post-move-in. I have a 2025 case in Liège where the owner spent 11 days without water because the initial SWDE invoice was in the contractor’s name — and the contractor had since moved.

Pitfalls to avoid

  • Don’t sign the minutes without the meter EAN code (18 digits) written clearly
  • Beware of contracts announcing “connections included” without specifying linear length
  • Sign your supplier contract only 10 days before commissioning
  • Keep the invoice for the temporary connection: it serves as proof of seniority

For official statistics on connection lead times in Wallonia, see statbel.fgov.be — construction and housing.

What next?

If your reception date is approaching and you doubt the state of progress of your connections, have your technical file validated by a third-party expert. My practice offers a Breyne Law advisory service covering this documentary check, or a free quote for a one-off expertise.

Before reception
Secure your connections before the reception minutes
Request a free quote

Need an expert for your reception?

Reply within 24h · free quote · no commitment. Coverage Brussels & Wallonia.